When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

Rotate the rectangle 90∘ clockwise about the origin.
How many moles in 13 grams of C 2 H6 ? show work
help it due by tonight and I have no clue how to do it
Can someone help me !!!
is My answer correct?
what was the difference between the founders of Connecticut and the founder of Rhode Island????have a great day ahead :) ​
Enter the number that belongs in the green box PLEASE HELP FAST
List adjectives that describe the emotions of the cartoon.
the open rule for a bill in the Senate means that: can be added to it?​
What is the distance from Jto K? 10 8 6 K(-3, 5) • - 10 -8 -6 4 2 2 4 6 8 10 -4 -6 • (-8, -7) -8 -10