it takes 8 labours 6days to complete a certain job.how many labours would complete the job in 15 days.​

Respuesta :

lakminirsenarath lakminirsenarath
  • 30-07-2021

Answer:

Step-by-step explanation:

Required man days to complete the job = 8 * 6

                                                                   = 48 Man Days

Required labors to complete the job by 15 days = 48/15

                                                                               = 3.2

It means, it is required 4 labors can complete the certain work by 15 days

Answer Link

Otras preguntas

I’m confused on this one
Plzzz answer !!!! Answer ASAP plz , would appreciate that
What is the most common chemical in a plant's cell wall?
1. Expansion will always come with additional expenses True or False 2. Whether the business owner likes the type of business he or she is in is not important
How was the Black Death spread throughout Europe? Contaminated crops Infected fleas Airborne bacteria Bacteria in water sources
If G=H, find the perimeter of FGH
In the Pythagorean Theorem, a2 + b2 = c2, which letter stands for the hypotenuse? a b c
Which treaty was the first major agreement between members of the Five Tribes and the US government? A. Treaty of Hopewell B. Treaty of New York C. Treaty of Pa
Given the equation 2Mg(s) + O2(g) → 2MgO(s) + 72.3 kJ, is this an endothermic reaction?
PLEASE HELP ME FOR EXTRA POINTS AND BRAINLIEST ANWSER