It takes 2 workers 6 days to paint a mansion. How many days would it take 4
workers to do the same job?

Respuesta :

dontmindme3
dontmindme3 dontmindme3
  • 01-03-2021

Answer:

2 workers = 6 days

4 workers = 3 days

Step-by-step explanation:

If it takes 2 workers 6 days, if you seep up the process with 4 workers, you would divide the days by 2 because you multilpied the workers by 2. So, it would take 3 days with 4 workers. I hope that makes sence.

Answer Link

Otras preguntas

12 pleaseeeee help meeeee!
Michael Jordan es muy alto. ______ es atletico.
Document A: A quote from the Mayor of San Francisco in a newspaper article It is my firm belief that an exclusion act, even more stringent than the present one,
y = 3/5x + 26 find the value of y when x =12 Pls do as soon as possible will mark as brainiest if you do with step by step explanation
If a report contains financial data that you want to analyze, you can export the report as a(n) _____ file.
Elle aime ____ école.lelalesl'
Okay Guys plz plz help like really 40 - 4k^3 k=2 and this:^ is the power to some like the power of 3
Khalid joins a security team where he is assigned an SOC developer role and has to build different teams under SOC. Which of the following teams should he build
Why was the United States described as a “police officer” in Latin America under President Theodore Roosevelt?
I will mark brainlist please help 1) Businesses often call their stores and warehouses bricks and clicks. • true • false 2) Start-up is a newly formed business