The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ______________.
a) function point
b) ratio
c) apportion
d) consensus
e) learning curves

Respuesta :

parisannthornton parisannthornton
  • 04-08-2021
The answer is e) learning curves
Answer Link

Otras preguntas

Help me on this question plz plz
How do you derive the drift velocity equation (I = nAve)?
the process that removes metabolic waste products from an organism is known as
If a=3 and b=5, what is the value of 3a + b to the power of 2?
Write a newspaper headline about the Boston tea party from the points of view of a loyalist and a patriot. Explain your headlines.
how does art inspire some people
what is the theory that tax cuts can raise supply called
You just priced what it would cost to buy vinyl floor tiles at the local tile store. They quoted you $3.29 per tile. When you went home you found the same exact
During a windstorm, part of the top of a flagpole breaks off. The broken top portion touches the ground at an angle of 65degrees 14feet from its base. How tall
What is party-as-organization?