8 students take 18 hours to construct a raft.
If the raft needs to be completed 12 hours earlier, calculate how many more students are needed.

Respuesta :

devishri1977
devishri1977 devishri1977
  • 04-08-2021

Answer:

16

Step-by-step explanation:

Students                      8       x

Time taken (hours)     18     18 - 12 = 6

If number of students increases, the work will completed in less hours.

So inverse proportion

[tex]x =\frac{18*8}{6}=3*8 = 24[/tex]

Additional students required = 24 - 8 = 16

Answer Link

Otras preguntas

Which is not an appropriate indicator of whether or not a baby is getting enough to eat? a. normal growth b. regular sleeping pattern c. normal elimination patt
The Boxer Rebellion led to an increase in Chinese nationalism. true or false
how can i evaluate (-7/10+0.15)÷(-0.125) please help
What landforms would Allied forces in the 1942 offensive from Casablanca Morocco to Tunisia have had to cross
Do most Colombians own cars?
Which of the following is not a benefit to using credit instead of cash? a. Using credit can help you build a good credit rating. b. Using credit allows you to
Leaving an automobile running in a closed garage or in a garage attached to the house - even with the garage door open could result in ___________ a. a citation
The deciding vote is also called the? 1. litigant. 2. law. 3. voting bloc. 4. swing vote.
Advances in which of the following areas increased globalization the most? technology, environmental protection, education technology, transportation, outsourci
choose some numbers to compare to 55 use = and <,>