contestada

5. If 15 men can finish a work in 16 days in how many days will 8 men can finish the same work? a. 15 b. 20 c. 30 d. 42​

Respuesta :

davism19 davism19
  • 02-08-2022

Answer:

C. 30

Step-by-step explanation:

15 men do work in 16 days

This means that 7.5 men (15/2) would do that same work in 32 days (16x2).

If the number of men increase, the amount of days decrease.

8 men would do that work in 30 days

8 men > 7.5 men

30 days < 32 days

Answer Link
profereyes12122
profereyes12122 profereyes12122
  • 05-08-2022

Answer:

Option c.

Step-by-step explanation:

It is an inverse proportion, fewer workers more days to finish the job.

15 -----16

8 ----- x

x = (16)(15)/8 = 240/8 = 30 days

Hope this helps

Answer Link

Otras preguntas

Someone help me on some marketing questions
In which organelle does cellular respiration occur? Question 2 options: Chlorplast Mitochondria Golgi Apparatus Nucleus
Bacteria reproduce asexually by ...
what is the next step in evaluating an online source after checking its reliability? A. Locate it's bibliography and search for those sources B. Determine if it
what is computer memory measured in​
why did the people who rear animal move from place to place​
The diameters of bolts produced in a machine shop are normally distributed with a mean of 5.11 millimeters and a standard deviation of 0.07 millimeters. Find th
i need help plz, can u help me?
What do you understand by 'BMI'?​
Patrick randomly selects a marble from a bag , records the color and then returns the marble to the bag . After 40 trials , he has recorded 14 red marbles 12 bl