If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

What right did natives have to their land?
A radioactive substance has a half-life of 7 hours. If a sample of the substance has an initial mass of 2000g, estimate the instantaneous rate of change in mass
Which state did not attend the Constitutional Convention which meet at Independence Hall in Philadelphia? and why answer and i will make brainlist
how do I learn spanish
What’s harder in college chemistry or physiology???
What was the largest native American tribe in Texas and what was their biggest struggle?
Imagine you're working in an emergency department of a large hospital. The paramedics call the ED to tell them they are about to arrive with an unconscious woma
6x+3y=24 3x-3y=-6 Solve the system using elimination (explain steps)
Why does your brain do some tasks automatically?
7th-grade math help me, please :(